The Caboolture Hospital Redevelopment Project commenced in November 2019. Stage 1 of the project is due to be completed in 2023 and will deliver

By 2023, the Caboolture Hospital Redevelopment will deliver:

By 2023 Caboolture Hospital Redevelopment will deliver 130 new beds
  • NEW CLINICAL SERVICES BUILDING
  • NEW MULTI-STOREY CARPARK
  • 130 NEW BEDS
  • EXPANDED SERVICES
  • REFURBISHMENT PROGRAM

All dates subject to change

Timeframe Milestone
April 2020 ·         New Mental Health Short Stay Unit COMPLETE
May 2020 ·         New Temporary Staff Carpark COMPLETE

·         Construction of Temporary Main Entry COMMENCED

·         Construction of new entry off McKean Street COMMENCED

June 2020 ·         Medical Records Refurbishment Stage 1 COMPLETE

·         New pathways around Mental Health and Community Oral Health Services COMMENCED

September 2020 ·         New Temporary Main Entry at rear of hospital OPENS

·         New Public Carpark at rear of hospital OPENS

·         New Temporary entry off McKean Street OPENS

October 2020 ·         Paediatric Outpatients DEMOLISHED

·         Demolition of Front Main Entry COMMENCES

Q1 2021 ·         New intersection off McKean Street OPENS

·         Arrival of first tower crane onsite