Development timeline2023-11-16T09:22:29+10:00

Development timeline

The new Clinical Services Building (CSB) is scheduled to open and welcome its first patient in 2023. Further refurbishment of targeted spaces within the existing hospital is due to be completed in 2024. The Multi-Storey Carpark will open in line with the new CSB in 2023, providing more than 1,000 parking spaces in a mix of multi-storey and at-grade facilities.

The Caboolture Hospital Redevelopment will deliver:

  • NEW CLINICAL SERVICES BUILDING
  • NEW MULTI-STOREY CARPARK
  • 130 NEW BEDS
  • EXPANDED SERVICES
  • REFURBISHMENT PROGRAM

All dates subject to change

Timeframe Milestone

April 2020

New Mental Health Short Stay Unit COMPLETE

May 2020

New Temporary Staff Carpark COMPLETE

June 2020

Medical Records Refurbishment Stage 1 COMPLETE

New pedestrian footpaths around Mental Health and Community Oral Health COMPLETE

September 2020

New Temporary Main Entry OPENED

New Public Carpark at rear of hospital OPENED

New Temporary entry off McKean Street OPENED

October 2020

Former Paediatric Outpatients DEMOLISHED

Former Front Main Entry DEMOLISHED

New Fluoroscopy / Mammography Room COMPLETE

November 2020

Clinical Services Building Construction COMMENCED

February 2021

Multi-Storey Carpark Construction COMMENCED

March 2021

New intersection off McKean Street OPERATIONAL

First tower crane ARRIVED

April 2021

Second tower crane ARRIVED

August 2021

Operational Commissioning activities COMMENCED

BEMS Building construction COMMENCED

September 2021

Third tower crane ARRIVED

Early 2023

Kitchen Refurbishment COMPLETE

Mid 2023

New BEMS Building Complete

2023

New Clinical Services Building OPENS

New Multi-Storey Carpark OPENS

2024

Refurbishment program (target spaces) in existing hospital COMPLETE

Caboolture Hospital