Site Activity Updates
Metro North Hospital and Health Service is working closely with Lendlease Building to make sure the community is kept informed about the Caboolture Hospital Redevelopment.
To stay up to date on key construction activities, subscribe to Lendlease’s fortnightly Site Activity Updates. Updates will be sent to your inbox every fortnight.
Site activity update – Monday 4 to Friday 15 September 2023
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Monday 7 to Friday 18 August 2023
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Monday 24 to Friday 4 August 2023
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Wednesday 12 to Friday 21 July 2023
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Monday 26 June to Friday 7 July 2023
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Tuesday 13 to Friday 23 June 2023
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Tuesday 30 May to Friday 9 June 2023
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Tuesday 16 to Friday 26 May 2023
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Tuesday 2 to Friday 12 May 2023
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Monday 17 to Friday 30 April 2023
No works will take place over the Easter break with site closed from Friday 7 April, and reopening Monday 17 April. The project hotline, 1300 144 425 is operational during this time and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Monday 3 to Friday 14 April 2023
No works will take place over the Easter break with site closed from Friday 7 April, and reopening Monday 17 April. The project hotline, 1300 144 425 is operational during this time and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Site activity update – Tuesday 21 to Friday 31 March 2023
Ongoing installation of hydraulics, mechanical, fire protection, electrical services and lifts. Ongoing façade infill and screen installation.
Site activity update – Tuesday 7 to Friday 17 March 2023
The underground works for the new power supply connection are now completed with minor reinstatement and landscaping works within road reserves to finish.
Site activity update – Tuesday 21 February to Friday 3 March 2023
The underground works for the new power supply connection are now completed with minor reinstatement and landscaping works within road reserves to finish.
Site activity update – Monday 6 to Friday 17 February 2023
The underground works for the new power supply connection are now completed with minor reinstatement and landscaping works within road reserves to finish.
Site activity update – Tuesday 24 January to Friday 3 February 2023
Ongoing installation of hydraulics, mechanical, fire protection, electrical services and lifts.
Site activity update – Wednesday 11 to Friday 20 January 2023
We hope you have enjoyed the festive season and are ready for an exciting year ahead as the Caboolture Hospital Redevelopment Projects head to completion. We will continue to keep you updated on construction activities and any impacts throughout the year.
Site activity update – Monday 28 November to Friday 9 December 2022
The underboring works for the new power supply connection are now completed. The next phase of works is pulling new underground cables and reinstatements works between the McKean Street roundabout and the substation on Jensen Road.
Site activity update – Monday 14 to Friday 25 November 2022
Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.
Site activity update – Monday 31 October to Friday 11 November 2022
The underboring works for the new power supply connection are now completed. The next phase of works is pulling new underground cables and reinstatements works between the McKean Street roundabout and the substation on Jensen Road.
Site activity update – Monday 17 to Saturday 29 October 2022
Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.
Site activity update – Tuesday 4 to Friday 14 October 2022
Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.
Site Activity Update – Monday 19 to Friday 30 September 2022
Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.
Site Activity Update – Monday 5 to Friday 16 September 2022
Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.
Site Activity Update – Monday 22 August to Friday 2 September 2022
Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.
Site Activity Update – Monday 8 to Friday 19 August 2022
Ongoing fit-out and façade activities, including installation of high-level services for hydraulics, mechanical, fire protection, electrical and flooring. Internal wall framing and sheeting on Levels 1 and 2. External glazing and cladding on Levels 3 and 4. Formwork, reinforcement, and concrete pour activities for the Central Energy Building.
Site Activity Update – Monday 11 to Friday 22 July 2022
Works to connect power supply to the new Clinical Services Building is ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. These works will take approximately three months to complete (subject to weather and ground conditions). Please see map below for alignment and locations of temporary work sites.