Site Activity Updates2021-09-07T08:20:47+10:00

Site Activity Updates

Metro North Hospital and Health Service is working closely with Lendlease Building to make sure the community is kept informed about the Caboolture Hospital Redevelopment.

To stay up to date on key construction activities, subscribe to Lendlease’s fortnightly Site Activity Updates. Updates will be sent to your inbox every fortnight.

Site activity update – Monday 14 to Friday 25 November 2022

Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.

Sign-up to receive updates about the Caboolture Hospital Redevelopment

Terms and Conditions Your name, email address and organisation will be disclosed to The Rocket Science Group LLC (Mailchimp) for the purposes of providing you with information on the Caboolture Hospital Redevelopment. Mailchimp provides online platforms that can be used to create, send and manage emails. Personal information collected by the Queensland Health is handled in accordance with the Information Privacy Act 2009. You can opt out of receiving this information by using the ‘unsubscribe’ service provided by Mailchimp in every email. You are entitled to access any of your personal information that has been supplied to Mailchimp. You are also entitled to edit or delete that information, unless Mailchimp is required by law to retain it. For more information, please refer to the Mailchimp privacy policy. For information about how Queensland Health protects your personal information, or to learn more about your rights to access your personal information, please visit to our Privacy Statement and Disclaimer page.

Site activity update – Monday 17 to Saturday 29 October 2022

Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.

Site activity update – Tuesday 4 to Friday 14 October 2022

Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.

Site Activity Update – Monday 19 to Friday 30 September 2022

Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.

Site Activity Update – Monday 5 to Friday 16 September 2022

Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.

Site Activity Update – Monday 22 August to Friday 2 September 2022

Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.

Site Activity Update – Monday 8 to Friday 19 August 2022

Ongoing fit-out and façade activities, including installation of high-level services for hydraulics, mechanical, fire protection, electrical and flooring. Internal wall framing and sheeting on Levels 1 and 2. External glazing and cladding on Levels 3 and 4. Formwork, reinforcement, and concrete pour activities for the Central Energy Building.

Site Activity Update – Monday 11 to Friday 22 July 2022

Works to connect power supply to the new Clinical Services Building is ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. These works will take approximately three months to complete (subject to weather and ground conditions). Please see map below for alignment and locations of temporary work sites.

Site Activity Update – Monday 27 June to Friday 8 July 2022

Works to connect power supply to the new Clinical Services Building is ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. These works will take approximately three months to complete (subject to weather and ground conditions). Please see map below for alignment and locations of temporary work sites.

Site Activity Update – Monday 13 to Friday 24 June 2022

Works to connect power supply to the new Clinical Services Building is ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. These works will take approximately three months to complete (subject to weather and ground conditions). Please see map below for alignment and locations of temporary work sites.

Site Activity Update– Fortnight commencing Monday 30 May 2022

Works to connect permanent power supply for the new Clinical Services Building have commenced. This is the first stage of the works which involves an under-bore near the south-eastern corner of the McKean Street roundabout across to the north-eastern side to connect existing conduits.

Site Activity Update– Fortnight commencing Monday 16 May 2022

Works to connect permanent power supply for the new Clinical Services Building have commenced. This is the first stage of the works which involves an under-bore near the south-eastern corner of the McKean Street roundabout across to the north-eastern side to connect existing conduits.

Site Activity Update– Fortnight commencing Tuesday 3 May 2022

Works to connect permanent power supply for the new Clinical Services Building have commenced. This is the first stage of the works which involves an under-bore near the south-eastern corner of the McKean Street roundabout across to the north-eastern side to connect existing conduits.

Site Activity Update – Fortnight commencing Tuesday 19 April 2022

Works to connect permanent power supply for the new Clinical Services Building have commenced. This is the first stage of the works which involves an under-bore near the south-eastern corner of the McKean Street roundabout across to the north-eastern side to connect existing conduits.

Site Activity Update – Fortnight commencing Monday 4 April 2022

Works to connect permanent power supply for the new Clinical Services Building have commenced. This is the first stage of the works which involves an under-bore near the south-eastern corner of the McKean Street roundabout across to the north-eastern side to connect existing conduits.

Site Activity Update – Fortnight commencing Monday 21 March 2022

Works to connect permanent power supply for the new Clinical Services Building have commenced. This is the first stage of the works which involves an under-bore near the south-eastern corner of the McKean Street roundabout across to the north-eastern side to connect existing conduits.

Site Activity Update – Fortnight commencing 10 January 2022

The project team is adhering to the Queensland Government’s COVID-19 restrictions and essential works will continue onsite with all safety measures implemented. We continue to monitor and respond to all COVID-19 updates and requirements as per the Public Health Directions from the Chief Health Officer.

Caboolture Hospital

Reset

More information

Redevelopment Project Team
Phone:  (07) 5316 5464
Email: Caboolture_Projects@health.qld.gov.au

Back to top