Site Activity Update – Fortnight commencing Monday 21 February to Friday 4 March 2022

COVID-19 update

The project team is adhering to the Queensland Government’s COVID-19 restrictions and essential works will continue onsite with all safety measures implemented. We continue to monitor and respond to all COVID-19 updates and requirements as per the Public Health Directions from the Chief Health Officer.

Permanent power connection works for new Clinical Services Building

Works will commence this Wednesday, 23 February to connect permanent power supply for the new Clinical Services Building. The first stage of this work involves an under-bore from near the south-eastern corner of the McKean Street roundabout across to the north-eastern side to connect existing conduits.

Temporary changes to the footpath on either side of McKean Street will be in place during these works to ensure pedestrians can safely move around the worksites. There will be no impact to traffic. 

What to expect:

  • An under-bore rig, vac-truck and equipment set-up outside the Multi-Storey Carpark site.
  • A receival worksite on the northern corner of McKean Street and on Mewett Street.
  • Slight change to footpath locations with signage and a traffic controller in place to safety direct pedestrians. Access will be maintained at all times.
  • Traffic signage in place on Mewett Street, McKean Street and Central Lakes Drive.
  • Work commencing from this Wednesday, 23 February for approximately two weeks.
  • If this activity is delayed due to weather, it will take place on the next available workday.

Clinical Services Building and Central Energy Building sites

Construction activities:

  • Installation of precast planks for the internal hospital access road.
  • Construction of suspended slabs on Levels 3 and 4. Works include scaffold erection, formwork placement, reinforcement installation and concrete pouring.
  • Formwork, reinforcement and concrete pour activities for lift cores, stair cores and walls for the new Central Energy Building.
  • Initial fitout and façade activities including installation of high-level services for hydraulics, mechanical, fire protection and electrical.
  • Scaffold erection and commencement of blockwork for the Central Energy Building.
  • Installation of inground tanks. 

What to expect:

Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Multi-Storey Carpark site

Ongoing construction activities:

  • Installation of Level 3 suspended slabs.
  • Ongoing perimeter scaffold erection.
  • Formwork, reinforcement and concrete pour activities for lift cores and stair cores.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Building and Engineering Maintenance Services (BEMS) Building site

Construction activities:

  • Excavation and installation of ground beams.
  • Civil infrastructure activities including stormwater and drainage works.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

New storage facilities site (western side of hospital campus)

Construction activities:

  • Excavation and installation of footings and slab. Works include formwork placement, reinforcement installation and concrete pouring.

 What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP

2022-02-23T11:46:02+10:0023 February 2022|