Site activity update – Tuesday 4 to Friday 14 October 2022

Ongoing permanent power connection works for the new Clinical Services Building – between McKean Street and Jensen Road

The underboring works for the new power supply connection are now completed. The next phase of works is pulling new underground cables and reinstatements works between the McKean Street roundabout and the substation on Jensen Road.

What to expect:

  • Reduced speed limits, partial lane closures and footpath diversions along Pettigrew Street, Lindwall Street and Jensen Road as required to maintain safety for motorists and pedestrians. 
  • All works will take place within road reserves.
  • Traffic controllers safely directing pedestrians and vehicles through the work zones.
  • Every effort will be made to minimise construction impacts during these works.

Clinical Services Building and Central Energy Building sites

Clinical Services Building - Level 1

Clinical Services Building – Level 1

Construction activities:

  • Ongoing fit-out and façade activities including installation of services for hydraulics, mechanical, fire protection, electrical and lifts.
  • Internal wall framing and sheeting on Levels 1,2,3 and 4.
  • Floor finishes, painting and waterproofing activities on Level 1.
  • Ongoing blockwork, roof and waterproofing installation to Level 5.
  • Ongoing façade screen bracket install.
  • Formwork, reinforcement, and concrete pour activities for the Central Energy Building.
  • Demolition activities to existing Common Good kitchen.
  • Scaffold dismantle activities

What to expect:

  • Fit-out works will be undertaken on Saturday 8 October.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Multi-Storey Carpark site

Multi-Storey Carpark site

Multi-Storey Carpark site

Construction activities:

  • Formwork, reinforcement and concrete pours for internal ramps.
  • Fit-out activities including installation of high-level services, crash barriers and façade screens.
  • Preparations for tower crane removal, currently planned for Saturday 15 October.

What to expect:

  • Fit-out works will be undertaken on Saturday 8 October.
  • Tower crane removal on Saturday 15 October.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Building and Engineering Maintenance Services (BEMS) Building site (southern side of the hospital campus)

Construction activities: 

Multi-Storey Carpark site

Multi-Storey Carpark site

  • Formwork, reinforcement and concrete pour activities.
  • Scaffold and blockwork installation.
  • Structural steel infill activities.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

New storage facilities site (western side of hospital campus)

Construction activities:

  • Water tank filling.
  • Kerb, line marking and fencing installation.
  • Realignment of construction hoarding around the existing tank.
  • Piling activities for new pump house.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Loading Dock extension works (southern side of hospital campus)

Construction activities:

  • Roofing activities including sheeting, gutters and downpipes
  • Services fit-off

What to expect:

  • Increased construction activity and vehicle movements on the southern side of the hospital campus, near the public carpark.

Thank you for your patience during the construction of the Caboolture Hospital Redevelopment.


Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP