Share

Site activity update – Monday 31 October to Friday 11 November 2022

Ongoing permanent power connection works for the new Clinical Services Building – between McKean Street and Jensen Road

The underboring works for the new power supply connection are now completed. The next phase of works is pulling new underground cables and reinstatements works between the McKean Street roundabout and the substation on Jensen Road.

What to expect:

  • Reduced speed limits, partial lane closures and footpath diversions along Pettigrew Street, Lindwall Street and Jensen Road as required to maintain safety for motorists and pedestrians. 
  • All works will take place within road reserves.
  • Traffic controllers safely directing pedestrians and vehicles through the work zones.
  • Every effort will be made to minimise construction impacts during these works.

Clinical Services Building and Central Energy Building sites

Construction activities:

  • Ongoing installation of hydraulics, mechanical, fire protection, electrical services and lifts.
  • Ongoing façade installation.
  • Internal wall framing and sheeting on Levels 2,3 and 4.
  • Ceiling installation on Levels 1 and 5.
  • Floor finishes, painting and waterproofing activities on Levels 1 and 2.
  • Ongoing blockwork, joinery, and plant room wall cladding to Level 5.
  • Ongoing façade screen bracket install.
  • Blockwork activities for the Central Energy Building.
  • Demolition activities to existing Common Good kitchen.
  • Scaffold dismantle activities.
  • Tower crane removal currently planned for Saturday 12 November.
CSB Level 5 plant room

CSB Level 5 plant room

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
  • Tower crane removal on Saturday 12 November.

Multi-Storey Carpark site

Construction activities:

  • Formwork, reinforcement and concrete pours for external ramps.
  • Façade screening and crash barrier installation

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Building and Engineering Maintenance Services (BEMS) Building site (southern side of the hospital campus)

Construction activities: 

  • Scaffold and blockwork installation.
  • Structural steel infill activities.
  • Commencement of façade setout.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

New storage facilities site (western side of hospital campus)

Construction activities:

  • Water tank filling over four days from Thursday 3 to Monday 7 November. Please see attached notification for further details regarding this activity. 
  • Kerb, line marking and fencing installation.
  • Realignment of construction hoarding around the existing tank.

What to expect:

  • Exclusion zone in the adjacent easement during water filling (as per attached notification).
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Mortuary and Hearse Bay works (services block refurbishment works)

Construction activities:

  • Installation of hoarding and temporary fencing.
  • Monitoring equipment in place.
  • Commencement of demolition activities

What to expect:

  • Increased construction activity and vehicle movements on the southern side of the hospital campus, near the public carpark.

Thank you for your patience during the construction of the Caboolture Hospital Redevelopment.


Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP

2022-11-01T10:55:02+10:001 November 2022|
Back to top