Site activity update – Tuesday 21 February to Friday 3 March 2023

Permanent power connection works for the new Clinical Services Building

The underground works for the new power supply connection are now completed with minor reinstatement and landscaping works within road reserves to finish.

Clinical Service Building – February 2023

Clinical Service Building – February 2023

Clinical Services Building and Central Energy Building sites

Construction activities:

  • Ongoing installation of hydraulics, mechanical, fire protection, electrical services and lifts.
  • Ongoing façade infill and screen installation.
  • Internal wall framing and sheeting on Levels 3 and 4.
  • Ceiling installation on Levels 1, 2, 3 and 4.
  • FF&E activities on Level 1.
  • Floor finishes, painting and waterproofing activities on Levels 1,2,3,4.
  • Central courtyard construction.
  • Structural steel activities for the Central Energy Building.
  • In-ground structure for the linkways.

What to expect:

  • General construction works will take place on Saturday 25 February.
  • External artwork application on the CSB will take place between 6pm and 6am on Sunday 5 March.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Multi-Storey Car Park - Febrary 2023

Multi-Storey Car Park – February 2023

Multi-Storey Carpark site

Construction activities:

  • Roadworks on the hospital ring road between the multi-storey carpark and the private hospital.
  • Internal line marking.

What to expect:

  • Single lane closure on hospital ring road managed by traffic lights and traffic controllers. Carparking around private hospital area will be temporarily impacted during this activity.

Building and Engineering Maintenance Services (BEMS) Building site (southern side of the hospital campus)

Construction activities: 

  • Ongoing external facade cladding installation.
  • Ongoing sheeting, setting, sanding and painting to internal walls.
  • Services installation. 
  • Scaffold removal.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
  • Temporary resumption of carparks during scaffold removal activities

New storage facilities site (western side of hospital campus)

Construction activities:

  • Concreting activities, including form, reo and pouring for the new hydraulic pump room
  • Structural steel install

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Mortuary and Hearse Bay works (services block refurbishment works)

Construction activities:

  • Ongoing in-ground hydraulics.
  • Removal and existing asphalt pavement.
  • Ongoing in-ground structure activities.

What to expect:

  • Increased construction activity and vehicle movements on the southern side of the hospital campus, near the public carpark.
  • Noise during concrete cutting and breaking activities. Neighbours may experience some noise, dust, fumes and vibration impacts. Every effort will be made to minimise these impacts.

Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP