Site Activity Update – Fortnight commencing 9 August 2021
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
COVID-19 update
The project team is adhering to the Queensland Government’s COVID-19 restrictions and essential works continue onsite. Social distancing and cleaning protocols are just some of the measures being followed by the project team to reduce the impact of COVID-19.
Clinical Services Building and Central Energy Plant site
Ongoing construction activities:
- Installation of a new construction entrance off McKean Street.
- Installation of the suspended slabs on level 2. Works include scaffold erection, formwork placement, reo installation and concrete pouring.
- Installation of precast floor beams and precast planks.
- Concrete pours for lift and stair cores.
- Installation of services.
- Excavation works.
- Commencement of scaffold protection for the Common Good kitchen.
What to expect:
- Temporary footpath closure from early August, with pedestrian diversion in place (refer map below), for approximately 2 weeks, weather permitting, during construction of the McKean Street construction site entrance.
- Commencement of deliveries via the McKean Street construction site entrance.
- Minor traffic delays during delivery of pre-cast planks and suspended deck concrete pours.
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Multi-Storey Carpark site activities
Construction activities:
- Ongoing inground services.
- Pile trimming and pile cap concrete pours.
- Inground services installation.
What to expect:
- Increased construction activity and vehicle movements in this area.
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Building and Engineering Maintenance Services (BEMS) Building activities
Construction Activities
- Commencement of civil activities including excavation and back filling.
- Installation of a piling pad.
- Inground services work.
What to expect:
- Increase in vehicle movements along the south western side of the hospital campus.
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Construction activities on hospital ring road
Construction Activities
- Reinstatement works following the completion of drainage installation on the western side of the hospital campus.
What to expect:
- Single lane road closure of the west bound Bury Street access road, managed with traffic control.
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com | www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP