Site Activity Update – Fortnight commencing 23 August 2021

The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.

Clinical Services Building and Central Energy Plant site

Ongoing construction activities:

  • Installation of the suspended slabs on Level 2. Works include scaffold erection, formwork placement, reo installation and concrete pouring.
  • Installation of precast floor beams, precast planks and topping slabs.
  • Concrete pours for lift and stair cores.
  • Ongoing installation of services.
  • Civil activities on the western side of the site continue.
  • Placement of roadway beams and planks for the internal access road.

What to expect:

  • Increase in vehicles accessing the site via the new construction entrance located on McKean Street (refer map below).
  • A single lane closure along McKean Street will be in place on Saturday, 28 August and Saturday, 4 September for the placement of roadway beams and planks. Two-way traffic will be maintained under traffic control.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Multi-Storey Carpark site activities

Construction activities:

  • Installation of hydraulic and electrical services.
  • Concrete pours for lift and stair cores.
  • Delivery and erection of the third tower crane in early September.

What to expect:

  • Increased construction activity and vehicle movements in this area.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Building and Engineering Maintenance Services (BEMS) Building activities

Construction Activities

  • Commencement of civil activities including excavation and back filling.
  • Installation of a piling pad and piling rig mobilisation.
  • Inground services work.
  • Conduit relocation works to the project site offices located on the south western side of the hospital campus.

What to expect:

  • Increase in heavy vehicle movements along the south western side of the hospital campus.
  • Partial road closure during the floating in of large machinery and during piling pad excavation works. Two-way traffic will be maintained under traffic control.
  • Establishment of exclusion zone in easement area between the BEMS construction site and the Caboolture State High School for piling activities.
  • Temporary power shut down to the project site offices on Saturday, 28 August for the conduit relocations work.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

 Construction activities on the hospital’s internal ring road

Construction Activities

  • Ongoing reinstatement works following the completion of drainage installation on the western side of the hospital campus.

What to expect:

  • Single lane road closure of the west bound Bury Street access road, managed with traffic control.
  • Weekend construction works on Saturday, 28 August to complete the reinstatement works on the western side of the hospital campus.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP