Site Activity Update – Fortnight commencing 1 November 2021

The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.

Clinical Services Building and Central Energy Plant site

Ongoing construction activities:

  • Installation of Level 2 and 3 suspended slabs. Works include scaffold erection, formwork placement, reo installation and concrete pouring.
  • Installation of precast floor beams and planks for internal hospital access road.
  • Concrete pours for lift and stair cores.
  • Installation of inground services.
  • Continuing fitout and façade installation.
  • Detailed excavation on the western side of the construction site.

What to expect:

  • The Clinical Services Building construction site will operate on Saturday, 6 November, between 6am and 5pm.

Road line marking, McKean Street intersection

Finalisation of road line markings to McKean Street will be installed week commencing Monday 8 November.

To complete this work safely, a partial lane closure will be in place for approximately one day (weather permitting). The exact date is yet to be confirmed, but will be between Monday, 8 November and Friday, 12 November.

What to expect:

  • Partial lane closure on McKean Street with two-way traffic and pedestrian access maintained.
  • Traffic controllers safely directing pedestrians and vehicles through the work zone (where required).
  • Reduced speed limit along McKean Street.
  • Neighbours may experience some noise during these works. Every effort will be made to minimise noise impacts.

 Multi-Storey Carpark site activities

Construction activities:

  • Scaffold erection and formwork placement.
  • Level 2 concrete pour.
  • Formwork, reinforcement, and concrete pouring for stair cores.
  • Installation of electrical services.

What to expect:

  • Increase in construction activity in this area. 
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Building and Engineering Maintenance Services (BEMS) Building activities

Construction activities:

  • Installation of stormwater and drainage pipes. 
  • Commencement of substructure activities.

What to expect:

  • Increase in construction activity in this area.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

New storage facilities site (western side of hospital campus)

Construction activities:

  • Installation of inground services.
  • Concrete pour for ground slab.

What to expect:

  • To maintain safety, a single lane closure on the hospital ring road, near the existing storage facility will remain in place until mid-November (weather permitting).
  • Temporary traffic lights are in place with one-way access maintained. Motorists may experience short delays during this temporary closure period.
  • Emergency services’ vehicle access will be prioritised.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

 

Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP