Site Activity Update – Fortnight commencing 29 November 2021

The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.

Clinical Services Building and Central Energy Plant sites

Construction activities:

  • Installation of Level 2 and Level 3 suspended slabs. Works include scaffold erection, formwork placement, reo installation and concrete pouring.
  • Formwork, reinforcement and concrete pour activities for lift cores, stair cores and the substation ground slab.
  • Fitout and façade commencement activities including installation of high-level services for plumbing, air-conditioning vents, fire protection and electrical.
  • Detailed excavation on the western side of the construction site for placement of in-ground tanks.

What to expect:

  • The Clinical Services Building construction site will operate on Saturday, 4 and Saturday, 11 December, between 6am and 6pm.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Multi-Storey Carpark site activities

Construction activities:

  • Installation of Level 2 suspended slabs.
  • Ongoing perimeter scaffold erection up to Level 2. 
  • Formwork, reinforcement and concrete pour activities for stair and lift cores.
  • Ongoing installation of electrical services.

What to expect:

  • The Multi-Storey Carpark construction site will operate on Saturday, 4 and Saturday, 11 December, between 6am and 6pm.
  • Perimeter scaffold will extend past the height of the ground level hoardings.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Building and Engineering Maintenance Services (BEMS) Building activities

Construction activities:

  • Excavation and installation of ground beams.
  • Civil infrastructure activities including drainage works.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

New storage facilities site (western side of hospital campus)

Construction activities:

  • Installation of concrete blade columns.
  • Continued installation of inground services.

What to expect:

  • To maintain safety, a single lane closure on the hospital ring road, near the existing storage facility will remain in place until early December (weather permitting).
  • Temporary traffic lights are in place with one-way access maintained. Motorists may experience short delays (maximum waiting time of one minute) during this temporary closure period.
  • Emergency services’ vehicle access will be prioritised.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP