Site activity update – Monday 14 to Friday 25 November 2022
Ongoing permanent power connection works for the new Clinical Services Building – between McKean Street and Jensen Road
The underboring works for the new power supply connection are now completed. The next phase of works is pulling new underground cables and reinstatements works between the McKean Street roundabout and the substation on Jensen Road.
What to expect:
- Reduced speed limits, partial lane closures and footpath diversions along Pettigrew Street, Lindwall Street and Jensen Road as required to maintain safety for motorists and pedestrians.
- All works will take place within road reserves.
- Traffic controllers safely directing pedestrians and vehicles through the work zones.
- Every effort will be made to minimise construction impacts during these works.
Clinical Services Building and Central Energy Building sites
Construction activities:
- Ongoing installation of hydraulics, mechanical, fire protection, electrical services and lifts.
- Ongoing façade installation.
- Internal wall framing and sheeting on Levels 2,3 and 4.
- Ceiling installation on Levels 1 and 5.
- Floor finishes, painting and waterproofing activities on Levels 1 and 2.
- Ongoing blockwork, joinery, and plant room wall cladding to Level 5.
- Ongoing façade screen bracket install.
- Blockwork activities for the Central Energy Building.
- Demolition activities to existing Common Good kitchen.
- Scaffold dismantle activities.
- Tower crane removal currently planned for Saturday 3 December.
What to expect:
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
- Tower crane removal on Saturday 3 December.
Multi-Storey Carpark site
Construction activities:
- Formwork, reinforcement and concrete pours for external ramps.
- Façade screening and crash barrier installation.
What to expect:
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Building and Engineering Maintenance Services (BEMS) Building site (southern side of the hospital campus)
Construction activities:
- Scaffold and blockwork installation.
- Structural steel infill activities.
- Commencement of façade setout.
What to expect:
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
New storage facilities site (western side of hospital campus)
Construction activities:
- Kerb, line marking and fencing installation.
- Realignment of construction hoarding around the existing tank.
What to expect:
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Mortuary and Hearse Bay works (services block refurbishment works)
Construction activities:
- Installation of hoarding and temporary fencing.
- Monitoring equipment in place.
- Commencement of demolition activities.
What to expect:
- Increased construction activity and vehicle movements on the southern side of the hospital campus, near the public carpark.
- Thank you for your patience during the construction of the Caboolture Hospital Redevelopment.
Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com | www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP