Site Activity Update – Monday 16 to Friday 27 May 2022

Permanent power connection works for new Clinical Services Building

Caboolture Hospital Site Redevelopment map - 21 March 2022

The first stage of works to connect power supply to the new Clinical Services Building is complete. The second stage of works, which involves underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables has commenced. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. These works will take approximately three months to complete (subject to weather and ground conditions). Please see map below for alignment and locations of temporary work sites.

What to expect:

  • Reduced speed limits, partial lane closures and footpath diversions along Pettigrew Street, Lindwall Street and Jensen Road. Changes are anticipated to be in place for two to three weeks before moving to the next location.
  • All works will take place within road reserves. We do not anticipate the need to access private properties.
  • Some on street parking may be impacted temporarily.
  • Traffic controllers safely directing pedestrians and vehicles through the work zones.
  • Every effort will be made to minimise construction impacts during these works

Clinical Services Building and Central Energy Building sites

Construction activities:

  • Installation of precast planks for the internal hospital access road.

    Clinical Services Building construction site – May 2022

  • Construction of suspended slabs on Level 5. Works include scaffold erection, formwork placement, reinforcement installation and concrete pouring.
  • Formwork, reinforcement and concrete pour activities for lift cores, stair cores and walls.
  • Initial fitout and façade activities, including installation of high-level services for hydraulics, mechanical, fire protection and electrical.
  • Wall framing and sheeting on Levels 1 and 2.
  • Glazing and cladding on Level 1.
  • Formwork, reinforcement, and concrete pour activities for the Central Energy Building.
  • Ongoing blockwork for the Central Energy Building.
  • Installation of inground tanks.
  •  

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Multi-Storey Carpark site

Multi-Storey Carpark construction site – May 2022

Ongoing construction activities:

  • Installation of Level 5 suspended slabs.
  • Formwork, reinforcement and concrete pour activities for lift cores and stair cores.
  • Initial fitout activities including installation of high-level services for electrical.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Building and Engineering Maintenance Services (BEMS) Building site

Construction activities:

  • Excavation and installation of ground beams.
  • Civil infrastructure activities, including stormwater and drainage works.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

New storage facilities site (western side of hospital campus)

Construction activities:

  • Installation of suspended slab for the new oxygen storage tank. Works include formwork placement, reinforcement installation and concrete pouring.
  • Commencement of water tank construction.
  • Deliveries of steel structural beams to support the new water tank.

What to expect:

Aerial view

  • Minor delays to the hospital’s internal access road during steel beam deliveries. Two-way traffic will be maintained under traffic control.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Loading dock extension works (southern side of hospital campus)

Construction activities:

  • Initial services activities to the existing loading dock. Please see map for location.

What to expect:

  • Increased construction activity and vehicle movements on the southern side of the hospital campus, near the public carpark.

Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP