Site Activity Update – Monday 22 August to Friday 2 September 2022

Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.

Site Activity Update – Monday 8 to Friday 19 August 2022

Ongoing fit-out and façade activities, including installation of high-level services for hydraulics, mechanical, fire protection, electrical and flooring. Internal wall framing and sheeting on Levels 1 and 2. External glazing and cladding on Levels 3 and 4. Formwork, reinforcement, and concrete pour activities for the Central Energy Building.