Site activity update – Monday 17 to Saturday 29 October 2022

Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.

Site activity update – Tuesday 4 to Friday 14 October 2022

Works to connect power supply to the new Clinical Services Building are ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. Please see map below for alignment and locations of temporary work sites.

Back to top