Site Activity Update – Fortnight commencing 28 June 2021

The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.

NAIDOC Week | 4 July – 11 July

We acknowledge the Traditional Owners of the land, the Kabi Kabi (Gubbi Gubbi) people, and pay our respect to Elders past, present and future.  

We will commemorate this important week by attending NAIDOC events taking place at Caboolture Hospital.  

 Online Information Session

Last Thursday, 24 June, our Caboolture Hospital Project team hosted an online information session to provide our partners, neighbours and the broader community with an update on project progress and upcoming works scheduled for the coming months.

Thank you to everyone who joined the online event and if you have any outstanding questions, please contact our team via email at caboolturehospital@lendlease.com  

 Biofuels trial 

Lendlease has chosen the Caboolture Hospital Redevelopment project for a Biofuels trial. From early July, two of the three tower cranes plus booms, hoists, lighting and general construction power (as items are progressively installed) will run off biodiesel generators until mains power becomes available.

BioDiesel is produced from renewable sources and offers an opportunity to reduce the carbon emissions and other air pollution impacts from the use of diesel generators. Sustainability is one of Lendlease’s highest priorities and we aim to demonstrate the benefits of BioDiesel to encourage this sustainable practice within the construction industry.

Clinical Services Building and Central Energy Plant site

Ongoing construction activities:

  • Concrete pours to lift and stair core walls.
  • Continued installation of precast floor beams and precast planks.
  • Concrete pours for ground floor slab.
  • Ongoing installation of hydraulics and electrical services.
  • Ongoing civil activities for the central drainage channel and Central Energy Plant building

What to expect:

  • Increased construction activity in the area.
  • Minor traffic delays during delivery of pre-cast planks.
  • Large number of heavy vehicle movements during concrete pours.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

 Multi-Storey Carpark activities

Construction activities:

  • Installation of construction entrance off McKean Street.
  • Commencement of substructure activities for cores, crane and pump bases.

What to expect:

  • Increased construction activity and vehicle movements in this area.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
  • Changes in traffic conditions to the McKean Street / Mewett Street roundabout during installation of construction entrance.

 Building and Engineering Maintenance Services (BEMs) Building activities

Construction Activities

  • Ongoing installation of drainage services on the western side of the hospital campus.

These works will be undertaken in sections and will progressively move along the hospital’s internal ring road, from the southern end of the hospital campus towards McKean Street over the next three months (weather permitting).

  • Inground electrical diversion for existing sewer pumping station power supply. Switch over from existing to new.

What to expect:

  • Excavation works and installation of drainage pipes.
  • Single lane road closure of the west bound Bury Street access road, managed with traffic control.
  • Temporary removal of carparks along the western side of the Community and Oral Health carpark while works are underway.
  • Temporary removal of carparks adjacent to the existing sewer pumping station for a temporary generator.
  • Construction activity and vehicle movements near the Bury Street end of the hospital campus.
  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

 

 

Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP