Site activity update – Tuesday 24 January to Friday 3 February 2023

Permanent power connection works for the new Clinical Services Building

The underground works for the new power supply connection are now completed with minor reinstatement and landscaping works within road reserves to finish.

Clinical Service Building – January 2023

Clinical Service Building – January 2023

Clinical Services Building and Central Energy Building sites

Construction activities:

  • Ongoing installation of hydraulics, mechanical, fire protection, electrical services and lifts.
  • Ongoing façade infill installation.
  • Internal wall framing and sheeting on Levels 3 and 4.
  • Ceiling installation on Levels 1, 2 and 5.
  • FF&E activities on Level 1
  • Floor finishes, painting and waterproofing activities on Levels 1,2,3 and 5.
  • Fitoff activities to early access ICT rooms
  • Ongoing façade screen install.
  • Blockwork and structural steel activities for the Central Energy Building.
  • In-ground structure and services activities for the linkways

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Multi-Storey Carpark site

Construction activities:

  • Façade screening install.
  • Roadworks on the hospital ring road between the multi-storey carpark and the private hospital.
  • Internal line marking
  • External artwork stencilling to stair core

What to expect:

  • Single lane closure on McKean Street managed by traffic lights and traffic controllers.
  • Carparking around private hospital area impacted at times.
  • Additional lighting after hours during stencilling activity.
BEMS Building internal framing – January 2023

BEMS Building internal framing – January 2023

Building and Engineering Maintenance Services (BEMS) Building site (southern side of the hospital campus)

Construction activities: 

  • Roofing activities.
  • Ongoing façade framing and internal partition setout activities.
  • High level services install activities.
  • Structural steel installation at western end.
  • Scaffold removal to southern facade

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

New storage facilities site (western side of hospital campus)

Construction activities:

  • Scaffold and reinforcing activities for the new hydraulic pump room
  • Installation of two new fire pumps and decommissioning of old fire pumps

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Mortuary and Hearse Bay works (services block refurbishment works)

Construction activities:

  • Commencement of internal in ground hydraulics
  • Removal and existing external concrete ramps and asphalt pavement
  • Commencement of excavation and in-ground structure activities

What to expect:

  • Increased construction activity and vehicle movements on the southern side of the hospital campus, near the public carpark.
  • Noise during concrete cutting and breaking activities. Neighbours may experience some noise, dust, fumes and vibration impacts. Every effort will be made to minimise these impacts

Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP