Share

Site activity update – Tuesday 21 to Friday 31 March 2023

Permanent power connection works for the new Clinical Services Building

The underground works for the new power supply connection are now completed with minor reinstatement and landscaping works within road reserves to finish.

Clinical Services Building and Central Energy Building sites

Construction activities:

  • Ongoing installation of hydraulics, mechanical, fire protection, electrical services and lifts.
  • Ongoing façade infill and screen installation.
  • Internal wall sheeting on Levels 3 and 4.
  • Ceiling installation on Levels 1, 2, 3 and 4.
  • Fittings and fixtures installation on Levels 1 and 2.
  • Floor finishes, painting and waterproofing activities on Levels 1,2,3,4.
  • Central courtyard façade construction.
  • Fitout works commencing for the Central Energy Building.
  • Continued structural steel for the linkways.
  • Commencement of roofing for linkways.
  • Commencement of existing window infills.
  • Continuation of roadworks on mental health road.
  • Commissioning activities.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
  • Single lane closure on hospital ring road leading into mental health managed by traffic lights and traffic controllers.

Multi-Storey Carpark site

Construction activities:

  • Footpath works external to the car park.
  • Commencement of new road linking carpark to existing road
  • Internal line marking.

What to expect:

  • Single lane closure on hospital ring road managed by traffic lights and traffic controllers. Carparking around private hospital area will be temporarily impacted during this activity.

Building and Engineering Maintenance Services (BEMS) Building site (southern side of the hospital campus)

Construction activities: 

  • Ongoing external facade cladding installation.
  • Ongoing sheeting, setting, sanding and painting to internal walls.
  • Commencement of ceiling grids.
  • Commencement of flooring activities.
  • Ongoing services rough-in installation. 
  • Commencement of civil road works.
  • Reinstatement works to existing easement.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

New storage facilities site (western side of hospital campus)

Construction activities:

  • Metal wall cladding installation.
  • Installation of hydraulic pumps.
  • In-ground electrical and comms pits.

What to expect:

  • Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.

Mortuary and Hearse Bay works (services block refurbishment works)

Construction activities:

  • Ongoing in-ground structure activities.
  • Perimeter wall demolition
  • Commencement of high level service installation

What to expect:

  • Increased construction activity and vehicle movements on the southern side of the hospital campus, near the public carpark.
  • Neighbours may experience some noise, dust, fumes and vibration impacts. Every effort will be made to minimise these impacts.

Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com  |  www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP

2023-03-27T10:27:36+10:0027 March 2023|
Back to top