Site Activity Update – Fortnight commencing 12 July 2021
The project hotline, 1300 144 425 is operational and our team can be contacted from 6am – 6pm, Monday to Friday. If you are calling outside of these hours, please leave a detailed message and one of our team members will return your call on the next business day.
Clinical Services Building and Central Energy Plant site
Ongoing construction activities:
- Installation of a new construction entrance off McKean Street.
- Ongoing installation of precast floor beams and precast planks.
- Concrete pours for ground floor slab.
- Ongoing installation of services.
- Ongoing civil activities to the central energy plant building located on the western side of the Clinical Services Building construction site.
What to expect:
- Temporary footpath closure from Monday 19 July, with pedestrian diversion in place (refer map below), for approximately four days, weather permitting, during construction of the McKean Street entrance.
- Minor traffic delays during delivery of pre-cast planks.
- Large number of heavy vehicle movements during concrete pours and civil activities.
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Multi-Storey Carpark site activities
Construction activities:
- Ongoing substructure activities for cores, crane and pump bases.
What to expect:
- Increased construction activity and vehicle movements in this area.
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Construction activities on hospital ring road
Construction Activities
- Installation of drainage services continue along the western side of the hospital campus.
- These works are being completed in sections and moving progressively along the internal hospital ring road towards McKean Street (weather permitting).
What to expect:
- Excavation works and installation of drainage pipes.
- Single lane road closure of the west bound Bury Street access road, managed with traffic control.
- Temporary removal of carparks along the western side of the Community and Oral Health car park while works are underway.
- Temporary removal of carparks adjacent to the existing sewer pumping station for a temporary generator.
- Construction activity and vehicle movements near the Bury Street end of the hospital campus.
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Multi-Storey Carpark site activities
Construction activities:
- Ongoing substructure activities for cores, crane and pump bases.
What to expect:
- Increased construction activity and vehicle movements in this area.
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Construction activities on hospital ring road
Construction Activities
- Installation of drainage services continue along the western side of the hospital campus.
- These works are being completed in sections and moving progressively along the internal hospital ring road towards McKean Street (weather permitting).
What to expect:
- Excavation works and installation of drainage pipes.
- Single lane road closure of the west bound Bury Street access road, managed with traffic control.
- Temporary removal of carparks along the western side of the Community and Oral Health car park while works are underway.
- Temporary removal of carparks adjacent to the existing sewer pumping station for a temporary generator.
- Construction activity and vehicle movements near the Bury Street end of the hospital campus.
- Neighbours may experience some noise, dust and vibration impacts. Every effort will be made to minimise these impacts.
Find out more about the Caboolture Hospital Redevelopment Project. Lendlease Project Team Caboolture Hospital Redevelopment Project (CHRP) McKean St, Caboolture QLD 4510 1300 144 425 CabooltureHospital@lendlease.com | www.lendlease.com We acknowledge the Traditional Owners of country throughout Australia and recognise their continuing connection to land, waters and community. We pay our respect to them and their cultures and to Elders past and present. Lendlease Reconciliation Action Plan: lendlease.com/RAP