Development timeline
The Herston Quarter redevelopment commenced in early 2017. The transformation of Herston Quarter will take up to 10 years to complete and will be managed across several stages.

Date | Details |
---|---|
March – December 2017 | Stage 1 – Site enabling works Site enabling works, including site separation of existing services and diversion works. |
June – February 2018 | Stage 2 – Site preparation works Site preparatory works, including demolition of the former children’s hospital buildings and excavation. |
Early 2017 – Late 2020 | Stage 3 – Design and construction of the Surgical, Treatment and Rehabilitation Service (STARS) Design of the specialist public health facility. Construction of STARS commenced in April 2018. |
October 2018 –2020 | Stage 4 – New car park Design and construction of 1150 space Northern car park. Construction anticipated to start in 2019 with site preparation works anticipated to commence in late 2018. Demolition of Bramston Terrace car park follows completion and opening of the Northern car park. |
Early 2018 – Late 2020 | Stages 5-7 – Heritage precinct revitalisation Multiple design and construction phases across heritage buildings. |