Caboolture Hospital Redevelopment2022-06-21T11:49:46+10:00

Caboolture Hospital Redevelopment

Over the next three years, Caboolture Hospital will undergo a major expansion and redevelopment to build a bigger and better hospital with more health services and improved parking for the community.

By 2023, the $399.5 million project will deliver a new five storey Clinical Services Building, a new Multi-Storey Carpark, an expansion and refurbishment program that will enhance and modernise spaces within a number of areas of the existing hospital and the relocation of Building Engineering and Maintenance Services (BEMS) into a new facility.

The Caboolture Hospital Redevelopment provides the community with access to a modern health facility and new specialist healthcare services, meaning patients can be treated closer to home, rather than always having to travel to larger facilities for treatment.

Metro North Health is delivering the Caboolture Hospital Redevelopment and has appointed Lendlease Building as the Managing Contractor. This exciting project will make sure Caboolture Hospital continues to meet the health needs of the local community as the population grows over the coming years.

Project Overview
Development timeline
Site Activity Updates
Clinical design
Other projects
Other projects

Upcoming changes to Caboolture Hospital

Site Activity Update – Monday 27 June to Friday 8 July 2022

Works to connect power supply to the new Clinical Services Building is ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. These works will take approximately three months to complete (subject to weather and ground conditions). Please see map below for alignment and locations of temporary work sites.

Site Activity Update – Monday 13 to Friday 24 June 2022

Works to connect power supply to the new Clinical Services Building is ongoing. Works include underground investigations into existing Energex conduits, digging at existing pits, and pulling new cables. These works begin at the McKean Street roundabout and continue north along Pettigrew Street to the substation on Jensen Road. These works will take approximately three months to complete (subject to weather and ground conditions). Please see map below for alignment and locations of temporary work sites.

Site Activity Update– Fortnight commencing Monday 30 May 2022

Works to connect permanent power supply for the new Clinical Services Building have commenced. This is the first stage of the works which involves an under-bore near the south-eastern corner of the McKean Street roundabout across to the north-eastern side to connect existing conduits.

Caboolture Hospital

Reset

More information

Redevelopment Project Team
Phone:  (07) 5316 5464
Email: Caboolture_Projects@health.qld.gov.au